Product
Litigation
- Early Case Assessment
- Evidence Analysis
- Web Search
- Document Review
- Production Setup
- Connectors (Upcoming)
- Legal Research (Upcoming)
Transactional
- Contract Review
- Contract Intelligence
- Word Add-In
- Web Search (Upcoming)
- Connectors (Upcoming)
- Legal Research (Upcoming)
Solutions
Litigation
- Early Case Assessment
- Investigations & Subpoenas
- Trial Preparation
- Enterprise eDiscovery
- Cloud eDiscovery
Transactional
Who it’s for
Resources
Learn
Customers
Events & CLE
Review a Statement of Work’s scope-change procedure by tracing each change from request through assessment, pricing, approval, implementation, and acceptance. From the customer’s perspective, test whether the supplier can increase charges, extend dates, or reduce deliverables without appropriate authorization. Compare the procedure with the scope baseline and master agreement, then test requested enhancements, disputed corrections, and urgent work. The deliverable is a coordinated redline and clause-linked checklist recording the evidence, customer consequence, proposed response, decision owner, and disposition of each material issue.
When to use this workflow
Use this workflow when customer-side counsel reviews a new SOW, an amendment, or a supplier request that exposes weaknesses in existing change control. It suits implementation, development, migration, and managed-services projects where assumptions and customer dependencies affect price and timing.
The focus is the change procedure, not a complete services-contract review. This guide assumes US private commercial contracting without a specified governing state law. Contract rights depend on the actual language, governing law, facts, and deal context; the review recommendations are not universal legal requirements.
What you need
Assemble a version-controlled review set containing:
- The SOW, master agreement, amendments, purchase order, and precedence provisions.
- Specifications, deliverables, exclusions, assumptions, customer dependencies, and acceptance tests.
- Fee schedules, expense rules, milestones, staffing commitments, and change-request forms.
- Approval, notice, dispute, suspension, security, intellectual-property, and amendment provisions.
- For a live request, the supplier’s estimate, supporting correspondence, work status, and claimed delay.
- The customer’s approval delegations and dated negotiation checklist, including fallbacks and escalation thresholds.
Assign document identifiers and versions. Distinguish unavailable attachments from language absent in reviewed documents. Ask the project lead which specifications define completion: that baseline determines whether the supplier proposes additional work or seeks payment for existing obligations.
Use the template
Copy the Statements of Work — Scope-change checklist table into your working document or spreadsheet. Use one row per issue; combine linked provisions when they produce a single approval risk.
| ID | Source/version | Trigger | Evidence/gap | Customer effect | Proposed response | Owner/status | Decision date |
|---|---|---|---|---|---|---|---|
In Source/version, record the document ID, section, and relevant page. Trigger identifies the activating event: a request, failed assumption, disputed instruction, or emergency. Evidence/gap captures a short extract or accurate paraphrase and identifies missing material.
Explain the consequence in Customer effect. Use Proposed response for the edit, fallback, and reasoning, with longer analysis keyed to the row ID. Owner/status identifies the decision-maker and disposition. Record an agreed calendar date in Decision date; keep internal targets distinct from contractual notice deadlines. If timing is unresolved, assign responsibility for setting it.
Step by step
1. Establish the controlling scope and hierarchy
Read scope, exclusions, assumptions, and dependencies alongside the master agreement. Identify whether a SOW or change order can override master terms, and whether the proposed form could amend protections beyond scope, price, and schedule.
The NCR filing illustrates why document level matters. Development Services Exhibit §1.2 requires both parties to execute each SOW; the attached SOW form states a hierarchy placing the SOW above the Exhibit and Purchase Agreement. These are document-specific provisions, not a conclusion about precedence throughout the filed package. See Development Services Exhibit §1.2 and attached SOW form. (sec.gov)
Record relevant hierarchy clauses and unresolved conflicts. Propose express limits on what a change order may amend, rather than assuming master protections remain untouched.
2. Define what counts as a change
Test additions, substitutions, volume increases, revised dependencies, acceleration, and defect correction. Ask whether omitted implementation tasks are necessary to satisfy an existing deliverable or genuinely outside the agreed scope.
Separate requested expansion from clarification, correction, and estimating error. For a failed customer dependency, identify the promised input, due date, evidence of failure, supplier notice, mitigation, and resulting impact. Do not assume every failed assumption supports the entire requested fee or extension.
Record the disputed boundary, supporting clauses, and proposed treatment. If specifications cannot resolve it, assign technical clarification instead of treating the supplier’s label as determinative.
3. Separate assessment from implementation approval
Map who may request a change, commission an assessment, approve assessment charges, sign the change order, and direct implementation. Check both parties’ approval roles against amendment formalities. Internal spending delegations alone should not be treated as the contractual approval mechanism.
The NCR Change Request Form separates resources approved to study a request from authorization to implement it, while identifying affected work products, schedule, and price. This illustrates drafting architecture, not market practice. See Appendix 1, Attachment 1. (sec.gov)
Check whether email, tickets, meetings, or silence qualify as approval under the wording. Record separate gates, authorized roles, assessment caps, and the required approval record. Specify whether assessment charges remain payable if implementation is rejected.
4. Require a complete impact assessment
Check whether the supplier must identify affected deliverables, added and avoided costs, expenses, milestones, resources, dependencies, and revised acceptance tests before implementation approval.
For delay claims, request the affected milestone, causal explanation, mitigation, and options for continuing unaffected work. Consider credits for removed scope and whether rejecting a proposal leaves original obligations intact.
Quantify exposure only from supported rates, hours, or amounts. Route changes affecting data handling, ownership, security, or liability to the relevant reviewer. Record missing information as an approval condition, identifying who must supply it and when. Do not close the row merely because the supplier has supplied a total price.
5. Control pending, disputed, and urgent work
Read change control with notice, suspension, and dispute provisions. Determine whether the supplier may begin work, incur expense, suspend unaffected services, or extend dates before agreement.
Consider preserving undisputed performance while escalating the disputed item, subject to technical dependencies. For urgent work, define eligible circumstances, authorizing role, spending limit, temporary measures, documentation, and subsequent approval. A rejected emergency proposal should not leave the treatment of already incurred costs unexplained.
Check notice recipients, delivery methods, receipt rules, and any business-day definition used for response periods. Record the proposed treatment and unresolved operational constraints. If work has started, preserve that fact separately; later documentation does not establish that prior authorization existed.
6. Reconcile acceptance and payment
Trace changed deliverables into specifications, test plans, review windows, rejection notices, remediation, retesting, and milestone payments. Check whether revised dates compress testing or production use triggers acceptance before revised criteria are agreed.
The ICELOUNGE MEDIA filing’s SOW includes alternative deemed-acceptance triggers involving five business days without an approver response, material conformity, or production deployment even without satisfying acceptance criteria. It preserves Services Warranty claims, connects milestone acceptance to payment, and requires detailed written rejection within the testing period. These are contractual examples, not default rules. See SOW Acceptance and Rejection provisions. (sec.gov)
Record coordinated acceptance and payment edits. Identify unavailable test plans and decide whether limited deployment needs express treatment rather than relying on an informal understanding.
7. Test the procedure and close the review
Run three scenarios through the wording: an enhancement, a disputed correction, and urgent intervention. Identify the actor, evidence, permitted expenditure, continuing work, notice route, and approval record for each.
Prepare coordinated redlines and a decision summary. Separate drafting defects from business choices: an unclear approver needs clarification; accepting uncapped assessment charges requires a commercial decision.
Update every row with the agreed edit, accepted risk, or decision owner and date. Verify revised cross-references and attach the approved change specifications. The output should document the disposition of issues, not simply collect unfavorable clauses.
Worked example
Fictional scenario. All parties, documents, amounts, and provisions below are invented. Harbor Vale Foods is reviewing SOW S-07 v3 from Cedar Lantern Systems for a $240,000 inventory-interface implementation. Section 2.2 includes nightly transfers. Section 8 allows assessments at stated hourly rates with project-lead approval and treats five business days without objection to an implementation estimate as authorization to proceed.
Estimate E-02 proposes $28,000 for real-time transfers and $7,000 for retry handling. The customer wants real-time transfers. Its technical lead recalls discussing retry handling, but Specification Attachment B is unavailable. Section 6 treats production use as acceptance and ties milestone payment to acceptance; E-02 omits revised tests. Finance requires additional-spend approval, but §8 does not identify finance as an approver.
The fictional review team sets these internal decision dates; they are not contractual deadlines.
| ID | Source/version | Trigger | Evidence/gap | Customer effect | Proposed response | Owner/status | Decision date |
|---|---|---|---|---|---|---|---|
| SC-01 | S-07 v3 §8; E-02 | Estimate unanswered | Silence permits implementation; finance omitted | Requested $35,000 could proceed without spending approval | Delete silence approval; require authorized written approval to preserve control | Counsel + finance/open | October 20, 2026 |
| SC-02 | S-07 v3 §2.2; E-02 | Retry charge | Nightly transfers included; B unavailable; recollection unverified | $7,000 may duplicate baseline work; entitlement unresolved | Obtain B and compare obligations before pricing retry work | Technical lead/open | October 19, 2026 |
| SC-03 | S-07 v3 §6; E-02 | Production use | Use triggers acceptance; revised tests missing | Payment could precede validation | Agree tests and limited-deployment treatment before approval | Project lead + counsel/open | October 21, 2026 |
The review supports negotiating the desired enhancement without conceding the retry charge. It also prevents approval of a price from obscuring acceptance consequences. The team should not classify retry handling as extra work or correction until it obtains the missing specification and evaluates the evidence.
Common mistakes
- Treating assessment approval as permission to build. Separate analysis spending from implementation authorization.
- Making every failed assumption a paid change. Check responsibility, notice, causation, mitigation, and the actual effect.
- Reviewing change control in isolation. Reconcile amendment formalities, precedence, suspension, acceptance, and payment.
- Leaving emergency work unlimited. Define circumstances, approver, cap, documentation, and treatment of costs.
- Calling an unseen attachment “not present.” Mark it unavailable and assign retrieval; an incomplete review set does not establish contractual absence.
Final quality check
- Each material finding identifies its source version and clause or page.
- The baseline includes specifications, exclusions, assumptions, and dependencies.
- Assessment and implementation approvals are distinct and workable.
- Pricing covers removed work, expenses, and supported schedule effects.
- Pending, disputed, and emergency work have explicit treatment.
- Changed deliverables connect to tests, rejection, remediation, and payment.
- Source extracts and cross-references are verified; open issues have owners and decision dates.
Complete the workflow with DecoverAI
DecoverAI is the Legal Intelligence Platform for litigation and transactions. For this workflow, contract review in Word supports selecting the customer as represented party and supplying deal-specific instructions. Findings quote clauses, rank severity, locate text, and identify missing language as not present. The lawyer can edit or insert suggestions as ordinary tracked changes in the signed-in Word user’s name, or dismiss findings with reasons. Verify any absence finding against the complete review set. (decover.ai) Tabular review supports work across documents; this checklist remains your work product and legal judgment remains yours. Book a demo to discuss this SOW review workflow.
Frequently asked questions
Should every change require a signed change order?
Match formalities to the commitment. Distinguish operational clarifications from changes to fees, deliverables, dates, or risk allocation. Specify authorized roles and required records, consistently with amendment and notice provisions.
How should we review paid impact assessments?
Check scope, rates, cap, deliverable, and approver. State whether charges remain payable if implementation is rejected. Assessment approval should not inadvertently authorize implementation.
What if the supplier calls defect correction a change?
Compare specifications, acceptance criteria, warranties, and correction obligations. Record competing interpretations and missing technical evidence. Separate any commercial accommodation from a concession that additional payment is contractually due.
Can the master agreement handle change control alone?
Possibly. Verify incorporation, precedence, and SOW exceptions. The combined documents still need usable approvers, scope references, pricing inputs, and milestone treatment. Avoid inconsistent duplication in the SOW.
Sources
- NCR SEC Exhibit 10.1 — Development Services Exhibit, attached SOW form, and Change Request Form. Contractual examples, not general law or market-standard evidence.
- ICELOUNGE MEDIA SEC Exhibit 10.01 — SOW Acceptance and Rejection provisions. Contractual acceptance and payment wording, not default rules.
This guide is general information about legal workflows, not legal advice for any matter. It was drafted and reviewed with AI assistance. The worked example is fictional. Contract rights and procedure depend on the governing law, the actual wording, and the facts, so check the cited sources and the rules that apply in your jurisdiction before relying on it.