Construction Contracts

How to review key terms for Construction Contracts

Review construction contracts from the project owner’s perspective with a copyable checklist covering scope, GMP, changes, delay, payment, and risk allocation.

October 15, 2026  ·  9 min read
Book a Demo →

Review a construction contract from the project owner’s perspective by testing whether the complete document package allocates scope, price, schedule, change authority, payment, and completion risk consistently. Extract the operative language, compare it with the owner’s approved positions, and check dependencies before proposing redlines. The deliverable is a source-linked review checklist distinguishing drafting defects, commercial decisions, missing evidence, and jurisdiction-specific legal questions. Each material issue should identify a proposed response, a decision-maker, and a documented disposition.

When to use this workflow

Use this workflow when owner’s counsel or an in-house team receives a contractor’s draft, a revised guaranteed maximum price (GMP) package, or departures from the owner’s construction form. It also supports review before approving an amendment.

The task is contract review, not ongoing project administration. Test whether the proposed terms can be administered by the owner’s actual team, then identify decisions needed for approval.

This guide uses a US orientation. Private-contract rights depend on wording, governing law, facts, and project context. Research state-specific payment, lien, indemnity, notice, and limitations questions separately. The federal clause example below is not a private-contract rule; confirm incorporation, alternates, deviations, and the award’s controlling version before applying it.

What you need

Assemble the agreement, general and supplementary conditions, drawings, specifications, addenda, pricing exhibits, schedule, insurance requirements, bonds, amendments, and incorporated documents. Record unavailable items rather than assuming customary protection.

Obtain the owner’s instructions on delivery method, pricing model, budget, required completion dates, intended use, financing conditions, and procurement commitments. A fixed-price design-build review raises different design-allocation questions from a cost-plus construction-management review.

Also obtain the owner’s approved form and negotiation checklist, with fallback positions and escalation authority. Identify the baseline by version: it expresses an internal position, not market practice. Ask the project manager, cost consultant, insurance adviser, and finance team for constraints relevant to their areas.

Use the template

Use Construction Contracts — Contract review checklist as the companion work product. Copy this table into your working document or spreadsheet.

ID / topic Source / version Text / dependencies Owner exposure Priority / confidence Proposed response Decision owner Status / evidence gap

Use one row per actionable issue. Split clauses creating distinct price and schedule concerns. Identify the document, revision, section, and page where available. Preserve a short exact extract and relevant definitions or cross-references; link longer extraction notes by row ID.

Distinguish priority from confidence. A missing insurance exhibit may be high priority while leaving little confidence about intended coverage. Identify whether language is absent from supplied documents, potentially contained in an unavailable document, or inapplicable. Specify a redline, evidence request, commercial approval, or legal research question—not merely “review.” Record a target resolution date in the status field.

Step by step

1. Establish the package and review baseline

Create an inventory with stable document IDs and revision dates. Read incorporation and order-of-precedence provisions first. Check whether contractor qualifications, proposal exclusions, or addenda override the owner’s technical requirements.

Confirm delivery method and pricing structure with the business team. Do not rate a GMP as protective without reviewing exclusions, allowances, reimbursable-cost rules, and adjustment mechanisms. Identify the particular owner-form version used for comparison.

Record: package gaps, precedence conflicts, baseline version, and assumptions. Keep dependent findings open until missing documents are supplied or the uncertainty is expressly escalated.

2. Test scope against the price commitment

Trace the work through drawings, specifications, scope exhibits, exclusions, and design-responsibility clauses. Examine allocation of incomplete design, coordination gaps, site information, temporary works, testing, and commissioning.

For a GMP, distinguish allowances from contingency: identify permitted uses, approval rights, supporting records, reconciliation, and treatment of unused balances. Check savings allocation, reimbursable costs, audit access, and owner-directed procurement.

A historical SEC-filed agreement includes reasonably inferable work within its GMP and links adjustments to written change orders under referenced conditions. Section 10.2 conditionally permits a price-adjusting change order when the owner selects a different bidder despite a qualifying contractor recommendation. These illustrate allocation choices, not market standards. See §§1.1 and 10.2.

Record: each scope-price mismatch, supporting documents, and proposed allocation or clarification.

3. Review payment and completion together

Read payment applications, supporting evidence, disputed amounts, retainage, final payment, and completion definitions as a sequence. Check evidence of progress, payment for stored materials, subcontractor payment documentation, and release conditions.

Test substantial completion against intended occupancy, required testing, outstanding work, and responsibility for utilities, security, and maintenance. For phased turnover, ask which milestones trigger payment, warranty periods, insurance changes, and delay damages. Check final-completion requirements for manuals, warranties, as-built records, and training.

Identify applicable-law questions concerning withholding, payment timing, retainage, and lien waivers before recommending their final wording.

Record: payment prerequisites, completion evidence, requested changes, and legal questions. Assign finance and project-team decisions separately from counsel’s assessment.

4. Map change authority and adjustment routes

Separate who may request work, authorize performance, value changes, grant time, and approve final adjustments. Check delegated limits, lender approvals, emergency work, disputed directives, and obligations to proceed before price agreement. Distinguish technical approvals from authorization to increase cost or extend time.

Look for silence-based mechanisms. One historical private agreement treats a construction change directive as an approved change order if the contractor fails to communicate agreement or disagreement with proposed adjustments within ten days after delivery. That consequence belongs to the particular wording, not construction contracts generally. See §18.4.4.

Record: authority gaps, adjustment routes, notice requirements, disputed-work obligations, and proposed clarifications. Identify who must decide each delegation question.

5. Separate delay notices from delay remedies

Extract each notice’s trigger, day-count convention, recipient, permitted delivery method, required content, follow-up submissions, and stated consequence. Distinguish occurrence, knowledge, receipt, and delivery. Do not calculate dates from an unverified event.

Map time relief separately from money. Review owner-caused delay, weather, concealed conditions, concurrency, mitigation, acceleration, and overlapping change procedures. Ask the scheduling team what evidence would establish impact on contractual milestones.

For an incorporated basic federal default clause, FAR 52.249-10(b) conditions qualifying delay protection on specified causes and written notice within ten days from the delay’s beginning, unless extended. Extensions depend on the contracting officer’s factual assessment; the provision does not itself promise monetary delay compensation. FAR 52.249-10(b).

Record: notice mechanics, remedies as written, ambiguous interactions, and scheduling questions—not an assumed universal notice deadline.

6. Reconcile risk allocation and owner obligations

Read indemnity, insurance, bonds, liability caps, damages exclusions, warranties, correction duties, suspension, and termination together. Check whether caps or exclusions limit protection granted elsewhere. Ask the insurance adviser to assess coverage requirements and evidence; contractual indemnity is not a substitute for that assessment.

Compare default and convenience termination provisions, including notice, cure, payment consequences, committed materials, subcontract arrangements, and access to records. Examine dispute resolution, forum, and continued-performance provisions for consistency with the owner’s response options. Separate enforceability questions from commercial recommendations.

Extract owner duties too: site access, design information, approvals, payment, and coordination. Test whether the schedule accommodates them.

Record: conflicts, unconfirmed coverage, owner dependencies, proposed responses, and the person authorized to accept residual risk.

7. Convert findings into an approval package

Prepare focused redlines and an issue summary. Link each material change to its checklist row, rationale, fallback, and dependent provisions. Recheck price and time terms after changing scope or completion language.

Separate drafting corrections from budget, schedule, insurance, or executive decisions. Record accepted risks and compensating protection. Do not close an issue merely because wording was proposed: verify its inclusion in the approval draft and reconcile relevant exhibits.

Record: disposition, approved-language reference, remaining evidence, accountable reviewer, and resolution date. Preserve the reviewed version so the approval cannot be mistaken for approval of a later draft.

Worked example

Fictional scenario: Cedar Quay Learning LLC is reviewing a $24 million GMP contract with Larkspur Builders LLC for a private training center requiring phased occupancy. The package contains draft agreement DA-03, scope exhibit SE-02, and schedule SC-01. Referenced supplementary conditions are unavailable. All parties, documents, amounts, and clause wording in this example are fictional.

DA-03 includes commissioning, but SE-02 excludes integrated systems testing. DA-03 names only the owner’s director as the authorized change signer, while SC-01 assumes weekly field approvals without defining their effect. DA-03 ties final payment to substantial completion without expressly requiring closeout records. The missing conditions prevent a complete assessment.

ID / topic Source / version Text / dependencies Owner exposure Priority / confidence Proposed response Decision owner Status / evidence gap
R1 / Testing DA-03 §4; SE-02 ¶8 “Commissioning included”; “integrated systems testing excluded” Testing cost and occupancy uncertainty High / medium Reconcile testing scope and GMP Project lead; counsel Open; testing list and precedence missing
R2 / Changes DA-03 §9; SC-01 note 3 Director signs changes; field approvals undefined Approval assumptions may disrupt schedule High / medium Separate technical responses from price/time authority Owner director Open; delegation decision required
R3 / Closeout DA-03 §12 Final payment at substantial completion Payment may precede records delivery High / medium Specify deliverables; reconcile conditions Finance; counsel Open; supplementary conditions missing

R1 changes the recommendation from accepting the stated GMP to requiring a scope-and-price reconciliation. Commissioning terminology alone does not resolve the testing exclusion. R2 does not establish that unauthorized changes have occurred; it identifies an ambiguity that may be resolved without granting field personnel spending authority. R3 remains provisional because the missing conditions might contain relevant requirements. The owner should not receive an unqualified approval while those dependencies remain unresolved.

Common mistakes

  • Reviewing only the signature agreement. Obtain incorporated conditions and exhibits before concluding protection is missing or sufficient.
  • Treating the GMP as an absolute ceiling. Trace exclusions, allowances, procurement choices, and adjustment routes.
  • Combining notices into one deadline. Extract each trigger, recipient, required content, and consequence separately.
  • Demanding protections the owner cannot administer. Check approval periods, evidence requirements, and personnel capacity with the project team.
  • Accepting isolated redlines. Recheck definitions, caps, remedies, precedence, and exhibits after material revisions.

Final quality check

  • Every material finding identifies the reviewed version and clause or page.
  • Extracts and cross-references match the source documents.
  • Missing documents are distinguished from absent language.
  • Scope exclusions and pricing adjustments are reconciled or escalated.
  • Change authority, notice triggers, and time-versus-money remedies remain distinct.
  • Owner obligations have operational reviewers; jurisdiction-specific questions have legal reviewers.
  • Open issues have decision-makers and target dates; accepted risks have documented approval.
  • Redlines, exhibits, and the approval summary reflect the same package and dispositions.

Complete the workflow with DecoverAI

DecoverAI is the Legal Intelligence Platform for litigation and transactions. In its contract review workflow in Word, select the owner as the represented party and provide project-specific instructions. Findings quote clauses, rank severity, locate text, and identify missing language as not present. The lawyer can edit or insert suggestions as ordinary tracked changes in the signed-in Word user’s name and dismiss findings with reasons. Tabular review supports work across multiple documents; verify findings against the complete package. The checklist and approval decisions remain the legal team’s work product. Book a demo to discuss this construction-contract review workflow.

Frequently asked questions

Should we review price before general conditions?

Establish incorporation and precedence first, then review them together. Price protection may depend on exclusions, definitions, and adjustment rights in the conditions.

Can one checklist cover design-build and construction management?

Yes, with different questions. For design-build, examine design responsibility and performance criteria. For construction management, distinguish advisory services from construction obligations and examine trade procurement, reimbursable costs, and owner-retained responsibilities.

Does a delay notice create a payment right?

Do not assume so. Assess notice compliance, entitlement language, and remedy separately. Record whether the text addresses time, money, both, or neither clearly enough for approval.

What if an incorporated exhibit is missing?

Request it and identify dependent findings. The authorized owner decision-maker should decide whether to defer approval or accept a documented unresolved risk. Do not substitute presumed terms for missing evidence.

Sources

Historical agreements illustrate wording only; practical review recommendations are not statements of legal requirements.

This guide is general information about legal workflows, not legal advice for any matter. It was drafted and reviewed with AI assistance. The worked example is fictional. Contract rights and procedure depend on the governing law, the actual wording, and the facts, so check the cited sources and the rules that apply in your jurisdiction before relying on it.